search envelope-o feed check
Home Unanswered Active Tags New Question
user comment-o

Order of display for events in Scheduler Resource Mode

Asked by Dave
12 years ago.

Hello,

Is there a method of setting the order of display for overlapped events in the Scheduler Resource Mode? Currently it seems the longest duration event is first etc...

Also, is there a method of having all events for one day be overlaid on top of each other? I know it seems to do this when I print to bitmap.

Thanks,

Dave

Answer posted by Dan Letecky [DayPilot]
12 years ago.

You can user EventSortExpression property to specify order of overlapping events. See also here:

http://www.daypilot.org/daypilot-pro-6-2-sp3.html

This question is more than 1 months old and has been closed. Please create a new question if you have anything to add.