How to change the default holiday in schedular Control?
Hi,
In schedular control the holidays on saturday and sunday.
I want to change it to only sunday or anyother day.
Isthere any provision forthat?
Thanks
You can modify e.IsBusiness status for individual cells using BeforeCellRender event handler.
See also: http://doc.daypilot.org/scheduler/cell-customization/