search envelope-o feed check
Home Unanswered Active Tags New Question
user comment-o

Saturday et sunday in gantt chart

Asked by Michel
8 years ago.

Is it possible to exclude exclude saturday and sunday in the gantt chatr.

For example
: A task from 2015-07-01 to 2015-07-07 duration = 5 day because 4 and 5 juilly arent saterday and sunday

Thanks

Michel

Answer posted by Dan Letecky [DayPilot]
8 years ago.

It is possible to hide Saturdays and Sundays by creating a custom timeline:

http://doc.daypilot.org/gantt/timeline/

This way you can create a timeline that includes only the workdays.

If you want to display "duration" that doesn't include Saturdays and Sundays than you will have to calculate it yourself and store it in the database as a custom field (and display it in the Duration header column).

This question is more than 1 months old and has been closed. Please create a new question if you have anything to add.