Is there any feature for showing time range scheduling line for Parent resource?

Asked by Naveen
7 years ago.

i have a job (assume parent). for this job i have multiple operations. First operation start on 15th Sep and last operation ends on 25th Sep. Now i want display a time linr from 15th Sep to 25th Sep for Parent.

Is there any feature for showing time range scheduling line for Parent resource

Answer posted by Dan Letecky [DayPilot]
7 years ago.

At this moment the Scheduler doesn't generate summary events automatically.

However, you can generate it manually based on the DB data a display it in the parent row using the parent row id.