gantt daypilot angular link dots not visible if the task viewport is not initially visible

Asked by Anonymous
21 days ago.

gantt daypilot angular link dots not visible if the task viewport is not initially visible, that is draw a link from task A and task B is only visible by draging how to fix this

Answer posted by Dan Letecky [DayPilot]
17 days ago.

With autoScroll enabled, you should be able to scroll automatically to the target task while creating a link by dragging.

Comment posted by Anonymous
17 days ago.

@Dan Letecky my problem is not related to scrolling issue. My problem is, a task(Task C) is not initially in my viewport and I try to link a Task( Task A - is initially in my viewport) to Task C by dragging at that time link connecting dot is not visible in Task C. so i can’t able to link task. Any solution for this

Comment posted by Dan Letecky [DayPilot]
17 days ago.

Do you see the problem in the online demo as well (Progressive Task Rendering)?

Comment posted by Anonymous
17 days ago.

@Dan Letecky yes, the same issue in (Progressive Task Rendering) as well in horizontal scrolling