gantt daypilot angular link dots not visible if the task viewport is not initially visible, that is draw a link from task A and task B is only visible by draging how to fix this

Answer posted by Dan Letecky [DayPilot]
1 month ago.

With autoScroll enabled, you should be able to scroll automatically to the target task while creating a link by dragging.

Comment posted by Anonymous
1 month ago.

@Dan Letecky my problem is not related to scrolling issue. My problem is, a task(Task C) is not initially in my viewport and I try to link a Task( Task A - is initially in my viewport) to Task C by dragging at that time link connecting dot is not visible in Task C. so i can’t able to link task. Any solution for this

Comment posted by Dan Letecky [DayPilot]
1 month ago.

Do you see the problem in the online demo as well (Progressive Task Rendering)?

Comment posted by Anonymous
1 month ago.

@Dan Letecky yes, the same issue in (Progressive Task Rendering) as well in horizontal scrolling