user comment-o

Gantt: Allow multiple tasks in one row

Asked by Leo
4 days ago.

Hi there,

I know this might be a bit of a stretch - but we have a lot of tasks that belong together but are separated by weekends (as the individual tasks only stretch from monday to friday, but overall we have a duration of a month or so).

Similar to the task versions, would an ability to group multiple tasks together in one row be a possibility in the future?

Cheers
Leo

Answer posted by Dan Letecky [DayPilot]
1 day ago.

Hi Leo,

The Gantt Chart doesn’t support multiple tasks in the same row. You’d have to use the Scheduler component for this.

However, you can display the task as a single box and insert active areas with a different color/background for the non-business time segments (e.g., weekends).

You can look at the Scheduler examples on skipping non-business hours and apply the same approach to the Gantt Chart.