Retrieve ResourceId when Resizing or Editing Calendar

Asked by Anonymous
18 years ago.
How do I set and retrieve the ResourceId on the calendar just like I do the description, start, and end time?

The resourceid on the "e" argument is always empty.

Thanks
Comment posted by Dan Letecky
18 years ago.
It's taken from the data source field specified in DataResourceField property.