Short duration daypilot events show on the schedule just fine, but if an event lasts for several months, it may not show on the schedule. For example, if you create a development event that starts on Jan. 1, 2013 and ends on Oct. 1, 2013, the event is created, but it doesn't show up on the schedule. Changing the start date of the calendar to 1/1/13, the event appears.