Gantt control, moving tasks

Asked by Andrew Ames
8 years ago.

Say I have 5 tasks, and each task is linked to the one before it, if i move the first task is it possible to have all the other tasks move the same number of days?

so say task one is from 01/01/2016 to 03/01/2016

and task 2 is 04/01/2016 to 06/01/2016

I move task one so that it starts on the 02/01/2016 can it then make task 2 move to 05/01/2016 to the 07/01/2016?

thank you?