search envelope-o feed check
Home Unanswered Active Tags New Question
user comment-o

Create schedule with only start date and duration

Asked by Doganc
11 days ago.

Hi, i want to ask somethink,
i have tasks, resources those related tasks and durations of tasks,
for example,
Resource A,
Taks 1 : StartDate => Now(); - Duration 3 Days,
Task 2 : Starts with end of Task1 end date and Durtion 4 Days,
Task 3 : Starts with end of Task 2 end date and Duration 4 Days,

Can i use only this options and crate a schedule? is it possible?
Thanks

Answer posted by Dan Letecky [DayPilot]
10 days ago.

No, this is not supported at the moment. You'll need to calculate the start and end dates before displaying the data in DayPilot.

New Reply
This reply is
Your name (optional):