At this moment, the Gantt chart requires the exact date/time points when specifying the task end. For example, a task that ends on May 31, 2025 needs to use end: "2025-06-01T00:00:00"
.
The Scheduler lets you modify the end specification to date only using the eventEndSpec property, but it’s not available in the Gantt chart at the moment.