gantt chart end date issue

Asked by Anonymous
21 days ago.

when i add gantt chart in my UI, where the end date appears one day earlier in the DayPilot Gantt chart, Why? and how to solve this issue.

Answer posted by Dan Letecky [DayPilot]
17 days ago.

At this moment, the Gantt chart requires the exact date/time points when specifying the task end. For example, a task that ends on May 31, 2025 needs to use end: "2025-06-01T00:00:00".

The Scheduler lets you modify the end specification to date only using the eventEndSpec property, but it’s not available in the Gantt chart at the moment.